1. Welcome and sign in.

2. Introducing new neighbors: 104 Stethem Ferry Rd. Malik and Kayla Stephens.

3. "Thank You, Volunteers" message (repeat of the email sent to the community).

4. Community Administration

A. HOA Email address

A dedicated HOA email address has been established: chriverfarm.hoa@gmail.com.

All HOA communications should be directed to this email address. Work orders will be accepted through the HOA email or the CMA portal. Board members' personal email addresses should no longer be used for HOA business.

Text messages and phone calls should be reserved for emergencies only. At this time, the HOA does not have a designated emergency point of contact. Mitch has informed the Board that he is unable to continue serving in that capacity due to other commitments.

B. Community Website

The comm unity website, https://carriagehomesriverfarm.com/, is actively being developed.

Lisa Moghazy is managing the website. The goal is to make it a valuable resource for residents by providing:

Governing documents and HOA references

Community updates

City announcements and local events

For example, residents will be notified of events such as the Johns Creek Hazardous Waste Recycling Event on August 15, which is free but requires advance registration.

C. Pool Emergency Phone

Fred Mendoza researched alternatives to the existing pool emergency phone line that comply with emergency call requirements.

A Voice over Internet Protocol (VoIP) system has been identified as the recommended replacement for the current AT&T landline. Comcast can provide this service at approximately 40% of the current cost (about 2.5 times less expensive). Comcast has ordered a site survey for cable installation. The project is currently in progress.

D. Compliance Enforcement

The Board will begin enforcing basic community standards, including:

Parking: No long-term or overnight parking is permitted on community streets.

Garbage bins: Trash and recycling bins must be stored inside garages when not scheduled for collection.

Yard maintenance: Front and backyards are HOA common areas. Residents are expected to keep these

areas neat, orderly, and free of personal belongings or debris.

5. Financial Review and Updates (Emily)

A. Roof Loan Repayment

The Board requested that CMA realign the accounting for roof loan payments.

CMA is separating roof loan funds from the operating account, as the original accounting structure was incorrect. Funds collected from the roof loan and townhouse special assessments will be maintained in a separate account and used exclusively for loan repayment.

B. Special Assessment Status

As of July 3, 37% of townhouse owners had not yet paid the special assessment for roof loan.

Payments are not considered late untilJuly 31. The Board is closely monitoring payment status. No grace period will be provided after the due date. Delinquent accounts will be referred for legal collection immediately.

C. Year-to-Date Expenses

The Board is awaiting reconciled financial statements. Current areas with significant expenditures include:

Pool repairs

Water line repairs

Building 700 drainage project


6. Townhouse Repairs and Special Projects

A. Plumbing Repairs

Managed by Mitch (Paramount Plumbing):

503 S. River Farm sprinkler system leak- repaired

Two shutoff valve repairs between Buildings 400 and 500 - completed

1402 shutoff valve repair (Attempt #1) - completed

Managed by Fred (Fletch-Barney plumbing company):

2100 leak- repaired

Stethem Ferry island sprinkler heads capped- completed

Two additional shutoff valve repairs to permanently address the island leak- completed

1402 shutoff valve repair (Attempt #2) - completed

Two sprinkler heads on the island continue to leak. Precision Sprinklers has been contacted to complete those repairs.

The Board found that Paramount Plumbing's rates are generally higher than Fletch-Barney's. Both companies will remain available for emergency repairs.

Emily is working with CMA to request reimbursement for the high April water bill resulting from the leak near 503 S. River Farm. The water utility allows this type of adjustment only once every 12 months.

B. Building 700 Drainage Project

This is a major infrastructure project.

Approximately 90% of the drainage pipes in front of Building 700 were found to be non-functional, resulting in erosion, soil settlement, and sinking around Units 702 and 703. Continued deterioration presents a risk of structural damage.

Four companies were contacted, and three proposals were received. ROP Services LLC was selected based on:

Expanded scope of work

Repairs to all four front stoops in addition to the drainage installation

Competitive pricing

Positive recommendations from community residents

The project is currently underway.

C. Stucco Repairs

The Board has received reports of stucco damage at eight units. An inspection of all 32 townhouse units was initiated. Many contractors charge inspection fees; however, SIR performed visual inspections at no cost and provided building-specific repair estimates.

Three primary categories of damage were identified:

Chimney holes

Holes in other exterior locations

Cracks

The estimated total repair cost for all buildings is approximately $42,000.

Because of the project's size, the Board plans to budget phased stucco repairs beginning next year through the special assessments. Full completion will likely require several years.

D. Other Repair Requests

The Board reviewed additional maintenance requests:

Unit 202 honeybee infestation: bee relocation is the homeowner's responsibility. any necessary

structural repairs after removal will be completed by the HOA.

Rotten window trim: Low priority. No repairs are planned this year.

Damaged mailboxes: The Board is evaluating the most critical repairs.

Broken steps on the pathway to the river: the quote is being requested.

Additional drainage issues reported near Units 301 and 401.

Detached and sinking porches reported at Units 201 and 301.

7. Landscaping Update and 2027 Planning

The Board discussed several resident concerns regarding landscaping and met with Greenwood management for clarification.

Key points discussed:

Many overgrown shrubs require rejuvenation, which is typically performed during winter at additional

cost.

Greenwood trimmed only the azaleas this season.

Greenwood trims vegetation only up to approximately 12 feet.

Some homeowners maintain portions of their landscaping independently, making it difficult for

Greenwood to determine which areas fall under their maintenance responsibilities.

2027 Landscaping Goals

Revise the landscaping contract with a more detailed scope of work.

Develop a townhouse yard registry identifying HOA-maintained areas.

Establish a winter rejuvenation plan for overgrown landscaping.

8. Pool Status and Future Repairs

The community pool is the HOA's primary recreational amenity and is in deteriorating condition. Passing annual inspections has become increasingly difficult. Loss of the neighborhood pool will also result in loss of access to the River Farm community pool.

Work Completed in 2026

Partial pool drainage (by the company)

Pool coping replacement (Fred)

Expansion joint replacement (to be completed in Fall 2026)

Minor Repairs needed

Crack repairs

Bathroom repairs and painting

Faucet replacements

Major Repairs Needed

Pool resurfacing (estimated cost: $20,000)

Wooden deck railing repairs

Wooden deck rehabilitation

Concrete deck crack and surface repairs

Structural evaluation and reinforcement of pool foundation support pillars

9. 2027 Townhouse Repair Priorities and Sprinkler System Plans Townhouse Repair Priorities

High-priority repairs needed on townhouses:

Structural porch repairs

Drainage improvements near buildings

Stucco repairs

Retaining wall repairs (between pool and Building 201)

Sprinkler System

The current sprinkler system continues to experience frequent leaks and requires significant repairs.

The Board is considering restoring irrigation at:

The two entrance islands

The island at the bottom of Stethem Ferry

If the townhouse community chooses to fully restore the sprinkler system, the Board will obtain a comprehensive inspection and repair proposal. Any restoration would include service to all townhouse units and would be funded exclusively through a future special assessment.

Contact Lisa Moghazy lisa.moghazy@att.net or Linda Mendoza lindamargaret@bellsouth.net to

  • Update directory information

  • Provide website content and photos

  • Content suggestions

Socialize with neighborhood friends on Facebook